Shiploader (Darwin)

Construction Phase

  • Write the PLC program to control the Ship Loader
  • Site Commissioning for the control system and HMI ( panelview )
 

Ship Loader Auxiliary Conveyor

Dry Commissioning
  • Conveyor to transfer mineral from road truck unloading station to ship loader
 

Ship Loader Auxiliary Conveyor

  • Dry Commissioning Phase
 

Wet Commissioning Phase

  • Loading mineral to ship via remote ground controller
  • Travel along the ship while ship loading operation
  • photo taken during wet commissioning phase